Skip to main content

Public contracts of Saint-Romain-de-Popey · 2022 · Construction and buildings

Travaux MSP

€1.2M
maximum contract amount over 4 years — what was paid on it is not published
Signed on 5 September 2022 · ended around September 2026 · 4 yrs

That is at most ~€293k a year on average: a maximum too.

Company selected

SM Bertholon ÉlectricitéTravaux d'installation électrique dans tous locaux · registered office Vindry-Sur-Turdine (69490) · headcount 6 to 9 employees · SIREN 305834459

A contract awarded to 14 holders; above, the main holder. With it: Solosec, Libercier, C.G.L (Christian Gondy-Gilles Lucarella), Ets Cherpin, Création Bâtiment Cindo, Courbiere & Fils, Tachin, P.M.D.P., J Bastion (Ouest Lyonnais Renovation), Ets Lepine Freres et Fils, Menuiserie Durier - Bourrassaud, Design Concept Paysages, Comptoir des Revêtements. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

1 bid received

Median for this procedure in 2022: 4 bids, across 2484 comparable contracts. Open tender · awarded to 14 companies

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

The largest of the 10 contracts Saint-Romain-de-Popey published for 2022.

Other contracts of SM Bertholon Électricité in Saint-Romain-de-Popey

Cantine scolaire2023 · maximum over 2 years618€kCantine scolaire2023 · maximum over 18 months42€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Ferme et actualisable

Published amendments : 1

The 2 lots : 1.1 €M · 76 €k

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.