Skip to main content

Public contracts of Saint-Sauveur-le-Vicomte · 2021 · Professional services

Maîtrise d’oeuvre réhabilitation du complexe sportif

€70k
maximum contract amount over 2.5 years — what was paid on it is not published
Signed on 10 November 2021 · ended around April 2024 · 2.5 yrs

That is at most ~€29k a year on average: a maximum too.

Who won it

Cabinet Levillain EconomistesActivité des économistes de la construction · registered office Pont l'Eveque (14130) · headcount 3 to 5 employees · SIREN 448134460

A contract awarded to a consortium of 3 holders; above, the main holder. With it: Atelier d'Architectes de la Touques, Areha Enr. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

2 bids received

Median for this procedure in 2021: 3 bids, across 1019 comparable contracts. Simplified procedure · awarded to 3 companies

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 2

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.