Public contracts of Saint-Sorlin-d'Arves · 2026 · Construction and buildings

Rénovation de l’office de tourisme : maçonnerie

€177k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 1 June 2026 · running until about June 2028 · 2 yrs
Ongoing1 Jun 2028

That is at most ~€88k a year on average: a maximum too.

Company selected

3BTP (3 BTP)Travaux de terrassement spécialisés ou de grande masse · registered office Saint Sorlin d'Arves (73530) · headcount 10 to 19 employees · SIREN 488235714

The competition

1 bid received

Median for this procedure in 2026: 3 bids, across 23525 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 3 by amount of the 9 contracts Saint-Sorlin-d'Arves published for 2026.

Other contracts of 3BTP (3 BTP) in Saint-Sorlin-d'Arves

Travaux curage démolition sciage et grue pour rénovation ot2026 · maximum over 2 years100€kDevis terrassement voirie et réseaux divers pour rénovation ot2026 · maximum over 2 years55€kEntretien et déneigement2024 · maximum over 4 years2€M
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.