Public contracts of Saint-Sylvain · 2024 · Construction and buildings

Construction d’une MSP

Masselin

€56k
contract ceiling — what was paid on it is not published
Signed on 26 November 2024 · ended around November 2025 · 12 months

Who won it

Masselin ÉnergieTravaux d'installation électrique dans tous locaux · registered office Ifs (14123) · headcount 250 to 499 employees · SIREN 414732990
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.