Public contracts of Sainte-Foy-l'Argentière · 2026 · Construction and buildings

Électricité

€108k
maximum contract amount over 22 months — what was paid on it is not published
Signed on 30 April 2026 · running until about February 2028 · 22 months
Ongoing29 Feb 2028

That is at most ~€59k a year on average: a maximum too.

Company selected

Établissements NoallyTravaux d'installation électrique dans tous locaux · registered office Chazelles-Sur-Lyon (42140) · headcount 10 to 19 employees · SIREN 410348569

Number 6 by amount of the 7 contracts Sainte-Foy-l'Argentière published for 2026.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.