Skip to main content

Public contracts of Sainte-Marie-la-Mer · 2020 · Construction and buildings

Création d’une médiathèque à Sainte-Marie-la-Mer

€21k
maximum contract amount over 18 months — what was paid on it is not published
Signed on 2 August 2020 · ended around February 2022 · 18 months

That is at most ~€14k a year on average: a maximum too.

Company selected

MenardAutres travaux spécialisés de construction · registered office Orsay (91400) · headcount 200 to 249 employees · SIREN 393313358

Number 21 by amount of the 24 contracts Sainte-Marie-la-Mer published for 2020.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.