Public contracts of Sarrola-Carcopino · 2023 · Professional services

Maîtrise d’œuvre pour le groupe scolaire et la crèche Effrico

€1.6M
maximum contract amount over 4 years — what was paid on it is not published
Signed on 14 November 2023 · running until about November 2027 · 4 yrs
Ongoing14 Nov 2027

That is at most ~€404k a year on average: a maximum too.

Company selected

Batiserf IngénierieIngénierie, études techniques · registered office Fontaine (38600) · headcount 10 to 19 employees · SIREN 310719711

A contract awarded to a consortium of 11 holders; above, the main holder. With it: Structures Informatique Électricité Thermique Ingénierie et Conseils, Villa/Battesti Architectes et Associés, Etamine, Ctre Euro Mediter Prevention Incendie (Cepi - BET Incendie), CL Design, Studio DAP, On, Casasoprana & Pozzo DI Borgo Architectes, AGP Économie, Forma Archi & CO. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

4 bids received

Median for this procedure in 2023: 3 bids, across 8324 comparable contracts. Simplified procedure · awarded to 11 companies

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 2 by amount of the 4 contracts Sarrola-Carcopino published for 2023.

Other contracts of Batiserf Ingénierie in Sarrola-Carcopino

Maîtrise d’œuvre pour la construction d’un groupe scolaire et d’une…2023 · maximum over 4 years1.6€M
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.