Public contracts of Sauternes · 2022 · Construction and buildings

Extensions de la STEP Mahourat

€384k
maximum contract amount over 18 months — what was paid on it is not published
Signed on 27 October 2022 · ended around April 2024 · 18 months

That is at most ~€256k a year on average: a maximum too.

Company selected

Gironde TravauxConstruction d'autres bâtiments · registered office Toulenne (33210) · headcount 10 to 19 employees · SIREN 463200402

A contract awarded to 2 holders; above, the main holder. With it: Soc Études Instal Hydroelectri. The amount is the whole contract’s: the DECP does not publish each holder’s share.

Number 2 by amount of the 2 contracts Sauternes published for 2022.

Other contracts of Gironde Travaux in Sauternes

Aménagement des locaux annexes de l’ancienne école Saint-Pierre : gros…2024 · maximum over 12 months150€kAménagement locaux annexes2024 · maximum over 12 months140€kAménagement locaux annexes2024 · maximum over 12 months41€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.