Skip to main content

Public contracts of Schiltigheim · 2024 · Construction and buildings

Réalisation de travaux de mise en accessibilité des établissements recevant du public (ERP) de la Ville de Schiltigheim

Plâtrerie

€20k
maximum contract amount over 13 months — what was paid on it is not published
Signed on 17 December 2024 · ended around January 2026 · 13 months

That is at most ~€19k a year on average: a maximum too.

Company selected

Établissements Robert GeistelTravaux de menuiserie métallique et serrurerie · registered office Duttlenheim (67120) · headcount 20 to 49 employees · SIREN 305062986

The competition

36 bids received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 55 by amount of the 62 contracts Schiltigheim published for 2024.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Environmental considerations : Critère environnemental, Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.