Aménagement du front de mer du quartier Fond Lahaye à Schoelcher - travaux d' infrastructures de l’APIT

The largest contract Schœlcher awarded in 2020, out of 8.

Original label (DECP) : « Aménagement du front de mer du quartier Fond Lahaye à Schoelcher - travaux d' infrastructures de l’APIT » · Contract · Construction and Bâtiment · carried out in 97233

2.1€M
contract ceiling — what was paid on it is not published
Signed on 8 January 2020 · ended around October 2020 · 0.8 yrs
Ended8 Oct 2020

Who won it

Compagnie Antillaise de Routes et Autoroutes et D'Importation de Bitume MoterSIREN 379134687

The competition

Number of bids not published for that year: the field is only systematic from 2024.

Adapted procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

View the consolidated DECP (data.gouv.fr) ↗

The form of the contract

PriceRévisable
Published amendmentsnone

Other contracts of Compagnie Antillaise de Routes et Autoroutes et D'Importation de Bitume Moter in Schœlcher

Fourniture et livraison de béton prêt a l emploi et d agrégats pour la ville lot1 - béton prêt a l emploi2026600k€

Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.

Source: Public procurement — DECP (data.gouv.fr)·Data·Method
Aménagement du front de mer du quartier Fond Lahaye à Schoelcher -…: 2.1 M€, Schœlcher 2020 · Qipu