Aménagement du coeur de ville

Superstructure éclairage public

€191k
framework agreement: a maximum envelope for orders over 20 months, not spending — what was paid on it is not published
Signed on 28 May 2021 · ended around January 2023 · 20 months

That is at most ~€115k a year on average: a maximum too.

Company selected

SobecaConstruction de réseaux électriques et de télécommunications · registered office Anse (69480) · headcount 1,000 to 1,999 employees · SIREN 703780247

Number 26 by amount of the 35 contracts Scionzier published for 2021. It belongs to the policy Town planning and housing.

Other contracts of Sobeca in Scionzier

Intervention sur le réseau d’éclairage public et de fibre optique2022 · maximum over 12 months500€kRequalification du quartier du Crozet : éclairage et réseaux secs2021 · maximum over 18 months193€kInterventions sur le réseau d’éclairage public, 20202020 · maximum over 12 months221€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Révisable

Published amendments : 1

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.