Public contracts of Segré-en-Anjou Bleu · 2021 · Construction and buildings

Regroupement des école maternelle et élémentaire René Brossard à Noyant la Gravoyère

Charpente ossature bois bardage manque OS

€192k
maximum contract amount over 22 months — what was paid on it is not published
Signed on 21 June 2021 · ended around April 2023 · 22 months

That is at most ~€105k a year on average: a maximum too.

Who won it

Rebours Pere en FilsTravaux de charpente · registered office Pree-D'Anjou (53200) · headcount 50 to 99 employees · SIREN 348666769

Number 11 by amount of the 73 contracts Segré-en-Anjou Bleu published for 2021.

Other contracts of Rebours Pere en Fils in Segré-en-Anjou Bleu

Travaux2025 · maximum over 5 months93€kRemplacement couverture École G Verger à Nyoiseau2025 · maximum over 4 months91€kConstruction Atelier Mairie et locaux sociaux St Martin du Bois2025 · maximum over 14 months90€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : 3

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.