Public contracts of Six-Fours-les-Plages · 2025 · Professional services

Maîtrise d’oeuvre pour la construction d’une piscine extérieure couverte

€2.4M
maximum contract amount over 3 years — what was paid on it is not published
Signed on 15 December 2025 · running until about November 2028 · 3 yrs
Ongoing14 Nov 2028

That is at most ~€812k a year on average: a maximum too.

Company selected

Ingenierie Techniques de l'AcoustiqueIngénierie, études techniques · registered office Nantes (44000) · headcount 3 to 5 employees · SIREN 339332926

A contract awarded to a consortium of 9 holders; above, the main holder. With it: Arest, Geoterria, Mascherpa-Juppe Architectes, Tual, Fgeco, Bet Cerretti, Berthomieu Bissery Mingui, L'Essentielle. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

29 bids received

Median for this procedure in 2025: 1 bid, across 3432 comparable contracts. Contract awarded without prior advertising or competitive bidding · awarded to 9 companies

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 11 by amount of the 120 contracts Six-Fours-les-Plages published for 2025.

Other contracts of Ingenierie Techniques de l'Acoustique in Six-Fours-les-Plages

Maîtrise d’oeuvre relative au projet de construction d’une piscine…2025 · maximum over 5 years1.2€M
Contract details (procedure, price, amendments, lots)

Procedure : Marché passé sans publicité ni mise en concurrence préalable

Price : Forfaitaire

Published amendments : 3

Subcontracting declared : no

Environmental considerations : Clause environnementale

The 2 lots : 1.2 €M · 1.2 €M