Skip to main content

Public contracts of Soudan · 2024 · Construction and buildings

Chaufferie à bois : chauffage et électricité

€275k
maximum contract amount over 9 months — what was paid on it is not published
Signed on 29 July 2024 · ended around April 2025 · 9 months

Company selected

CB ÉlecTravaux d'installation d'eau et de gaz en tous locaux · registered office Saint-Maixent-L'Ecole (79400) · headcount 20 to 49 employees · SIREN 790674352

The largest of the 2 contracts Soudan published for 2024.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Mixte

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.