Skip to main content

Public contracts of Souillac · 2020 · Professional services

Maîtrise d’oeuvre pour travaux de réhabilitation et création de réseaux d’assainissement, d’adduction d’eau potable et pluvial

€27k
maximum contract amount over 14 months — what was paid on it is not published
Signed on 21 February 2020 · ended around April 2021 · 14 months

That is at most ~€23k a year on average: a maximum too.

Company selected

AltereoIngénierie, études techniques · registered office Venelles (13770) · headcount 100 to 199 employees · SIREN 453686966

Number 2 by amount of the 2 contracts Souillac published for 2020.

Other contracts of Altereo in Souillac

Elaboration de la cartographie des réseaux Eau Potable et Assainissement2021 · maximum over 12 months38€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.