Skip to main content

Public contracts of Soyaux · 2024 · Construction and buildings

Travaux de gros oeuvre, terrassements, raccordements réseaux pour l’installation d’un modulaire au stade Pierre Fournier

€68k
maximum contract amount over 2 months — what was paid on it is not published
Signed on 28 October 2024 · ended around December 2024 · 2 months

Company selected

Leonard BâtimentConstruction d'autres bâtiments · registered office Angouleme (16000) · headcount 20 to 49 employees · SIREN 308749837

The competition

1 bid received

Median for this procedure in 2024: 1 bid, across 3196 comparable contracts. Contract awarded without prior advertising or competitive bidding · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 4 by amount of the 14 contracts Soyaux published for 2024. It belongs to the policy Culture, sport and youth.

Contract details (procedure, price, amendments, lots)

Procedure : Marché passé sans publicité ni mise en concurrence préalable

Price : Forfaitaire

Published amendments : 2

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.