Skip to main content

Public contracts of Stuckange · 2022 · Construction and buildings

Réaménagement et extension de l’école : gros œuvre

€89k
maximum contract amount over 4 months — what was paid on it is not published
Signed on 31 May 2022 · ended around September 2022 · 4 months

Company selected

JBTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Silly-En-Saulnois (57420) · headcount 1 or 2 employees · SIREN 910959246

Number 3 by amount of the 10 contracts Stuckange published for 2022.

Other contracts of JB in Stuckange

Réaménagement et extension de l’école : étanchéité2022 · maximum over 4 months30€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.