Public contracts of Talmont-Saint-Hilaire · 2023
Lot 2 - gros oeuvre démolition
The largest contract Talmont-Saint-Hilaire awarded in 2023, out of 45.
Original label (DECP) : « Lot 2 - gros oeuvre démolition » · Contract · Construction and Bâtiment · carried out in 85440
2€M
contract ceiling — what was paid on it is not published
Who won it
McbatSIREN 437536600The competition
Number of bids not published for that year: the field is only systematic from 2024.
Adapted procedure · awarded to 1 company
Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.
The form of the contract
PriceFerme et actualisable
Published amendments2
The 2 lots
Lot 122 December 2023987k€
Lot 222 December 2023987k€
Other contracts of Mcbat in Talmont-Saint-Hilaire
Lot 2 - gros oeuvre démolition2025987k€Lot 2 - gros oeuvre démolition20223M€Réalisation d’une extension d’une salle omnisports - Les Ribandeaux - Lot 02 Gros-œuvre Démolition2022984k€Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.