Public contracts of Tayrac · 2026 · Construction and buildings

Démolition et gros œuvre

€116k
maximum contract amount over 14 months — what was paid on it is not published
Signed on 13 March 2026 · running until about May 2027 · 14 months
Ongoing13 May 2027

That is at most ~€100k a year on average: a maximum too.

Who won it

SARL Bâtiment Courrege et FilsTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Baraqueville (12160) · headcount 10 to 19 employees · SIREN 324308964

The largest of the 7 contracts Tayrac published for 2026.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.