Skip to main content

Public contracts of Ternay · 2024 · Construction and buildings

Réhabilitation de la maison médicale en pôle santé-13 chauffage-ventilation-plomberie

€71k
maximum contract amount over 15 months — what was paid on it is not published
Signed on 17 December 2024 · ended around March 2026 · 15 months

That is at most ~€56k a year on average: a maximum too.

Company selected

Abitibi MaintenanceTravaux d'installation d'équipements thermiques et de climatisation · registered office Lentilly (69210) · headcount 20 to 49 employees · SIREN 423510627

The competition

2 bids received

Median for this procedure in 2024: 3 bids, across 48340 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 10 by amount of the 14 contracts Ternay published for 2024. It belongs to the policy Health and social care.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 1

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.