Skip to main content

Public contracts of Thiers · 2019 · Energy

Travaux de rénovation, réaménagement et mise en accessibilité école élémentaire moutier à Thiers

Courants forts/ courant faibles

€166k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 11 October 2019 · ended around October 2020 · 12 months

Company selected

Soc Auvergnate Installations ElectriquesTravaux d'installation électrique dans tous locaux · registered office Aulnat (63510) · headcount 10 to 19 employees · SIREN 498536416

Amounts paid

Electricity, gas and heating: €810k paid by Thiers in 2019, all suppliers together (its accounts). The accounts do not say what share went to Soc Auvergnate Installations Electriques.

Number 9 by amount of the 82 contracts Thiers published for 2019. It belongs to the policy Schools.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.