Travaux réseau eau potable réservoir pont bas et villages est

€38k
maximum contract amount over 17 months — what was paid on it is not published
Signed on 11 February 2019 · ended around July 2020 · 17 months

That is at most ~€27k a year on average: a maximum too.

Company selected

Auvergne ÉtudesIngénierie, études techniques · registered office Le Crest (63450) · SIREN 423865757

Number 41 by amount of the 82 contracts Thiers published for 2019. It belongs to the policy Streets and transport.

Other contracts of Auvergne Études in Thiers

Travaux renouvellement conduites eau potable secteur de felet2019 · maximum over 2 months25€kMaîtrise d’oeuvre pour le renouvellement des réseaux eaux potable…2018 · maximum over 7 months48€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.