Skip to main content

Public contracts of Thonon-les-Bains · 2022 · Construction and buildings

Drainage terrain de football-Mise en place d’un réseau de drainage et régénération du terrain de football annexe au complexe des Grangettes à Thonon-les-Bains

€77k
maximum contract amount over 2 months — what was paid on it is not published
Signed on 20 May 2022 · ended around July 2022 · 2 months

Company selected

Coseec FranceServices d'aménagement paysager · registered office La Balme-De-Sillingy (74330) · headcount 20 to 49 employees · SIREN 390713659

Number 51 by amount of the 95 contracts Thonon-les-Bains published for 2022.

Other contracts of Coseec France in Thonon-les-Bains

Terrain synthétique : terrassements, aire sportive et voirie et réseaux…2020 · maximum over 4 months884€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.