Public contracts of Thorigny-sur-Marne · 2024 · Construction and buildings

Aménagement de la cour de l’école primaire des Pointes

€267k
maximum contract amount over 4 months — what was paid on it is not published
Signed on 6 June 2024 · ended around October 2024 · 4 months

Company selected

Travaux Publics Île de FranceConstruction de réseaux pour fluides · registered office Lagny-Sur-Marne (77400) · headcount 20 to 49 employees · SIREN 344877808

The competition

2 bids received

Median for this procedure in 2024: 3 bids, across 48741 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 4 by amount of the 14 contracts Thorigny-sur-Marne published for 2024. It belongs to the policy Schools.

Other contracts of Travaux Publics Île de France in Thorigny-sur-Marne

Voirie, réseaux divers et aménagement des espaces publics2024 · maximum over 3.5 years5.4€MEntretien et aménagement de voirie, assainissement et voirie et réseaux…2021 · maximum over 4 years2€M
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : 2

Subcontracting declared : yes

Environmental considerations : Critère environnemental, Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.