Thyez: spending by policy area · 2025
Streets and transport
€1.4M
8% of 2025 spending · €215 per resident
€1.3M in 2024
Breakdown of this item’s spending
Click a line to see what it is made of
Largest works since 2023
Click a building site to see the contract
- Réseaux humides chemin des Rotzs, chemin du Noyer, route de Plessy et route de Châtillon2024 · Colas France (Établissement de Bonneville)€775k
- Réseaux humides chemin des Rotzs, chemin du Noyer, routes de Plessy et de Châtillon2024 · 2 contracts · 2 companies€775k
- Réseaux humides et recalibrage de la rue du Nanty2025 · Decremps BTP€150k
Who won this item’s contracts since 2023
Compared with towns of the same size
5% of the town’s running costs goes to this item. Towns of the same size: 2.6%.
Source: the town’s 2025 accounts (DGFiP), by public policy. Amounts paid in the year. Works and companies: published contracts, amounts at signature. See the source