Public contracts of Tosse · 2023
reconstruction ecole maternelle
Contract · Construction and Bâtiment · Travaux · carried out in 40230
5.5€M
contract ceiling — what was paid on it is not published
Who won it
O.B.M. Construction (Obm Construction)SIREN 343889309The competition
Number of bids not published for that year: the field is only systematic from 2024.
Adapted procedure · awarded to 1 company
Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.
The form of the contract
PriceFerme et actualisable
Published amendmentsnone
Subcontracting declaredyes
The 2 lots
Lot 16 July 20232.7M€
Lot 26 July 20232.7M€
Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.