Skip to main content

Public contracts of Toul · 2025 · Construction and buildings

Travaux de réhabilitation et de construction des vestiaires Club House du Stade Pont Bernon à la Ville de Toul ; Couverture, Bardage, Etanchéité

€140k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 13 January 2025 · ended around January 2026 · 12 months

Who won it

Soprema EntreprisesTravaux d'étanchéification · registered office Strasbourg (67100) · headcount 2,000 to 4,999 employees · SIREN 485197552

The competition

3 bids received

Median for this procedure in 2025: 3 bids, across 48929 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 8 by amount of the 26 contracts Toul published for 2025. It belongs to the policy Culture, sport and youth.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Social considerations : Critère social

Environmental considerations : Critère environnemental

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.