Public contracts of Toulouse · 2026 · Construction and buildings

Travaux de construction d’un équipement mutualisé pour le quartier malepere

Lots 4, 6, 8, 9, 18 et 19

€705k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 2 October 2026 · running until about December 2028 · 2 yrs
Ongoing1 Dec 2028

That is at most ~€325k a year on average: a maximum too.

Company selected

Compagnie Générale d Entreprise Moderne Construction Cgem ConstructionConstruction d'autres bâtiments · registered office Toulouse (31200) · headcount 50 to 99 employees · SIREN 518666029

The competition

5 bids received

Median for this procedure in 2026: 3 bids, across 23525 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 129 by amount of the 375 contracts Toulouse published for 2026.

Other contracts of Compagnie Générale d Entreprise Moderne Construction Cgem Construction in Toulouse

Travaux de réfection des menuiseries extérieures de l’école Etienne…2025 · maximum over 4 months421€kExtension de la salle d’armes louis julien/2025 · maximum over 11 months222€kConstruction du gymnase guilhermy et d’une salle d’activité2025 · maximum over 15 months173€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Social considerations : Clause sociale

Environmental considerations : Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.