Public contracts of Trémorel · 2022 · Construction and buildings

Rénovation énergétique de la salle polyvalente

Démolition · Gros oeuvre

€31k
maximum contract amount over 16 months — what was paid on it is not published
Signed on 28 June 2022 · ended around October 2023 · 16 months

That is at most ~€23k a year on average: a maximum too.

Who won it

Nicol Environnement (SNT)Travaux de démolition · registered office Ploufragan (22440) · headcount 0 employees · SIREN 433946381

The competition

11 bids received

awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 15 by amount of the 15 contracts Trémorel published for 2022.

Contract details (procedure, price, amendments, lots)

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.

Rénovation énergétique de la salle polyvalente: up to €31k over 16 months, Trémorel 2022 · Qipu