Public contracts of Trilport · 2022
MOE construction restaurant scolaire
The largest contract Trilport awarded in 2022, out of 3.
Original label (DECP) : « MOE construction restaurant scolaire » · Contract · Construction and Bâtiment · carried out in 77470
185k €
contract ceiling — what was paid on it is not published
Who won it
5-Cinq ArchitectureSIREN 381810852The competition
Number of bids not published for that year: the field is only systematic from 2024.
Adapted procedure · awarded to 5 companies
Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.
The form of the contract
PriceRévisable
Published amendmentsnone
Other contracts of 5-Cinq Architecture in Trilport
MOE travaux d’extension et création d’une classe à l’école maternelle La Charmoye202548k€Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.