Public contracts of Troisfontaines · 2025 · Construction and buildings

Mise aux normes accessibilité dojo

Démolition-gros oeuvre

€50k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 2 June 2025 · ended around June 2026 · 12 months

Who won it

Strubel SASConstruction d'autres bâtiments · registered office Hartzviller (57870) · headcount 20 to 49 employees · SIREN 359801305

Number 2 by amount of the 2 contracts Troisfontaines published for 2025.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.

Mise aux normes accessibilité dojo: up to €50k over 12 months, Troisfontaines 2025 · Qipu