Skip to main content

Public contracts of Tuffé Val de la Chéronne · 2021 · Construction and buildings

DLE ouest

€318k
maximum contract amount over 5 months — what was paid on it is not published
Signed on 3 December 2021 · ended around May 2022 · 5 months

Company selected

Dle OuestConstruction de réseaux pour fluides · registered office La Chapelle-Sur-Erdre (44240) · headcount 100 to 199 employees · SIREN 487549057

The largest of the 4 contracts Tuffé Val de la Chéronne published for 2021.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.