Skip to main content

Public contracts of Vallières-sur-Fier · 2020 · Construction and buildings

Etanchéité multicouches construction école maternelle et locaux périscolaires

€65k
maximum contract amount over 21 months — what was paid on it is not published
Signed on 15 July 2020 · ended around April 2022 · 21 months

That is at most ~€37k a year on average: a maximum too.

Company selected

Goncalves Freres EtancheiteTravaux d'étanchéification · registered office Chignin (73800) · headcount 6 to 9 employees · SIREN 534687983

Number 11 by amount of the 14 contracts Vallières-sur-Fier published for 2020.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : 3

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.