Public contracts of Vannes · 2020 · Construction and buildings
Travaux de peinture des classes de l’École Élémentaire Jacques Prévert
Les travaux sont répartis en 2 phases : · •Phase 1 : Juillet 2020 : 1 mois · •Phase 2 : Juillet 2021 : 1 mois · Peinture
That is at most ~€15k a year on average: a maximum too.
Company selected
PolychromeTravaux de peinture et vitrerie · registered office Ploeren (56880) · SIREN 849962782The competition
awarded to 1 company
Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.
Number 89 by amount of the 100 contracts Vannes published for 2020. It belongs to the policy Schools.
Contract details (procedure, price, amendments, lots)
Price : Forfaitaire
Published amendments : none
Subcontracting declared : no
Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.