Public contracts of Veigy-Foncenex · 2024 · Construction and buildings
Extension du bâtiment ABC
Centre de Loisirs / · Électricité courants forts et courants faibles
Company selected
Sdel Savoie LemanTravaux d'installation électrique dans tous locaux · registered office Chavanod (74650) · headcount 20 to 49 employees · SIREN 418736526A contract awarded to 3 holders; above, the main holder. With it: Mugnier'Elec (Mugnier' Elec). The amount is the whole contract’s: the DECP does not publish each holder’s share.
The competition
Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 3 companies
Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.
Number 12 by amount of the 14 contracts Veigy-Foncenex published for 2024.
Other contracts of Sdel Savoie Leman in Veigy-Foncenex
Construction d’une halle couverte et d’une buvette2025 · maximum over 7 months107€kRénovation et extension de la Crèche Arc-en-Ciel2025 · maximum over 3 months90€kContract details (procedure, price, amendments, lots)
Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds
Price : Forfaitaire
Published amendments : 3
Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.