Public contracts of Vergongheon · 2020 · Construction and buildings

Agrandissempent des vestiaires du stade municipal et changt de chaudière

CMF structures

€45k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 1 September 2020 · ended around September 2021 · 12 months

Company selected

CMF StructuresFabrication de structures métalliques et de parties de structures · registered office Massiac (15500) · headcount 50 to 99 employees · SIREN 491326401
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.