Réhabilitation énergétique du complexe sportif

€107k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 26 April 2024 · ended around April 2025 · 12 months

Company selected

Établissements LecuyerTravaux de couverture par éléments · registered office Ferrieres-En-Brie (77164) · headcount 20 to 49 employees · SIREN 678203977

Number 7 by amount of the 10 contracts Vernou-la-Celle-sur-Seine published for 2024.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 2