Public contracts of Vertou · 2020 · Construction and buildings

Changement des menuiseries extérieures de l’hôtel de ville de Vertou

€38k
maximum contract amount over 6 months — what was paid on it is not published
Signed on 10 January 2020 · ended around July 2020 · 6 months

Company selected

Juignet ArmandTravaux de menuiserie métallique et serrurerie · registered office Les Sorinieres (44840) · headcount 50 to 99 employees · SIREN 340539568

A contract awarded to 2 holders; above, the main holder. With it: Bouygues Énergies & Services. The amount is the whole contract’s: the DECP does not publish each holder’s share.

Number 19 by amount of the 32 contracts Vertou published for 2020.

Other contracts of Juignet Armand in Vertou

Travaux énergétiques et réaménagements intérieurs de l’hôtel de ville…2024 · maximum over 17 months258€kTravaux énergétiques et réaménagements intérieurs de l’hôtel de ville…2024 · maximum over 17 months148€kConstruction d’un accueil de loisirs sans hébergement : menuiseries…2019 · maximum over 14 months246€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : 2

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.