Public contracts of Vertou · 2019 · Construction and buildings

Reprise de l’isolation en sous-face de plancher dans des bâtiments communaux

€43k
maximum contract amount over 1 month — what was paid on it is not published
Signed on 15 October 2019 · ended around November 2019 · 1 month

Company selected

PlafisolTravaux de plâtrerie · registered office Le Pellerin (44640) · headcount 10 to 19 employees · SIREN 389044314

Number 44 by amount of the 64 contracts Vertou published for 2019.

Other contracts of Plafisol in Vertou

Salle Sèvre et Maine2022 · maximum over 1 month28€kConstruction d’un accueil de loisirs sans hébergement (ALSH)2019 · maximum over 14 months8€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.