Public contracts of Villard-Bonnot · 2022 · Construction and buildings

Extension et restructuration des sanitaires

École libération

€41k
maximum contract amount over 5 months — what was paid on it is not published
Signed on 30 May 2022 · ended around October 2022 · 5 months

Company selected

SASU CO-Bert (CO-Bert)Travaux de plâtrerie · registered office Villeurbanne (69100) · headcount 10 to 19 employees · SIREN 811237890

Number 10 by amount of the 20 contracts Villard-Bonnot published for 2022. It belongs to the policy Schools.

Other contracts of SASU CO-Bert (CO-Bert) in Villard-Bonnot

Construction d’un restaurant scolaire, école Victor Hugo2022 · maximum over 12 months47€kExtension et réaménagement de l’école maternelle république2020 · maximum over 11 months21€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

The 2 lots : 29 €k · 12 €k

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.