Maîtrise d’oeuvre de l’agrandissement de l’école

€125k
maximum contract amount over 18 months — what was paid on it is not published
Signed on 3 May 2021 · ended around November 2022 · 18 months

That is at most ~€84k a year on average: a maximum too.

Who won it

Alpes FluidesIngénierie, études techniques · registered office Albertville (73200) · headcount 6 to 9 employees · SIREN 401850599

A contract awarded to a consortium of 4 holders; above, the main holder. With it: Stebat, Khephren (Imhotep Architectes). The amount is the whole contract’s: the DECP does not publish each holder’s share.

The largest of the 2 contracts Villard-sur-Doron published for 2021.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Mixte

Published amendments : 4

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.