Gros œuvre, terrassement et réseaux

€679k
maximum contract amount over 13 months — what was paid on it is not published
Signed on 18 December 2019 · ended around January 2021 · 13 months

That is at most ~€626k a year on average: a maximum too.

Company selected

Travaux Entretien Bâtiment Midi-PyreneesTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Toulouse (31300) · headcount 3 to 5 employees · SIREN 501456479

The largest of the 15 contracts Villeneuve-lès-Bouloc published for 2019.

Other contracts of Travaux Entretien Bâtiment Midi-Pyrenees in Villeneuve-lès-Bouloc

Construction d’une maison médicale communale2019 · maximum over 10 months169€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : 2

The 4 lots : 170 €k · 170 €k · 170 €k · 169 €k

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.

Gros œuvre, terrassement et réseaux: up to €679k over 13 months, Villeneuve-lès-Bouloc 2019 · Qipu