Public contracts of Villeparisis · 2019 · Construction and buildings

Travaux d’accessibilité de la Maison Pour Tous

€29k
maximum contract amount over 8 months — what was paid on it is not published
Signed on 9 January 2019 · ended around September 2019 · 8 months

Company selected

Société Bosio et FilsTravaux d'installation d'eau et de gaz en tous locaux · registered office Montfermeil (93370) · headcount 0 employees · SIREN 668201445

Number 30 by amount of the 39 contracts Villeparisis published for 2019.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.