Public contracts of Villers-Canivet · 2023 · Construction and buildings

Rénovation thermique de l’école et de la salle des fêtes : bardage et zinguerie

€79k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 27 March 2023 · ended around March 2025 · 2 yrs

That is at most ~€40k a year on average: a maximum too.

Company selected

Entreprise Marie et CompagnieTravaux de couverture par éléments · registered office Remilly Les Marais (50570) · headcount 50 to 99 employees · SIREN 906180096

Number 2 by amount of the 2 contracts Villers-Canivet published for 2023.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : 1

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.