Skip to main content

Public contracts of Villeurbanne · 2019 · Construction and buildings

Mise en conformité accessibilité et sécurité du centre social cyprian les brosses et restructuration de la crèche Babil’home

€42k
maximum contract amount over 22 months — what was paid on it is not published
Signed on 11 September 2019 · ended around July 2021 · 22 months

That is at most ~€23k a year on average: a maximum too.

Company selected

Soc Études Realisations Elect LyonnaisesTravaux d'installation électrique dans tous locaux · registered office Saint-Priest (69800) · headcount 10 to 19 employees · SIREN 971502943

Number 60 by amount of the 84 contracts Villeurbanne published for 2019. It belongs to the policy Health and social care.

Other contracts of Soc Études Realisations Elect Lyonnaises in Villeurbanne

Rénovation des installations électriques du groupe scolaire Jean Jaurès2025 · maximum over 2.5 years207€kSurélévation du groupe scolaire Albert Camus2024 · maximum over 2 years72€kMise en conformité électrique du groupe scolaire edouard herriot…2019 · maximum over 6 months90€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.