Public contracts of Villiers-sur-Orge · 2023 · Construction and buildings

Construction de la halle ouverte : terrassement, assainissement, voirie

€155k
maximum contract amount over 9 months — what was paid on it is not published
Signed on 5 September 2023 · ended around June 2024 · 9 months

Company selected

Grands Travaux de l OrgeConstruction de réseaux pour fluides · registered office Saint-Michel-Sur-Orge (91240) · headcount 20 to 49 employees · SIREN 394868277

Number 7 by amount of the 17 contracts Villiers-sur-Orge published for 2023.

Other contracts of Grands Travaux de l Orge in Villiers-sur-Orge

Construction d’une halle ouverte à Villiers-sur-Orge : terrassement…2023 · maximum over 9 months155€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.

Construction de la halle ouverte : terrassement, assainissement,…: up to €155k over 9 months, Villiers-sur-Orge 2023 · Qipu