Public contracts of Vinay · 2024 · Transport and vehicles

Entretien maintenance et rénovation des installations d’éclairage public

€120k
framework agreement: a maximum envelope for orders over 4 years, not spending — what was paid on it is not published
Signed on 4 March 2024 · running until about March 2028 · 4 yrs
Ongoing4 Mar 2028

That is at most ~€30k a year on average: a maximum too.

Company selected

GreenalpDistribution d'électricité · registered office Grenoble (38000) · headcount 200 to 249 employees · SIREN 833619109

The competition

1 bid received

Median for this procedure in 2024: 3 bids, across 17972 comparable contracts. Open tender · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 12 by amount of the 19 contracts Vinay published for 2024.

Other contracts of Greenalp in Vinay

Raccordement >36 kva2026 · maximum over 12 months93€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Unitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.