Public contracts of Vittel · 2024 · Construction and buildings

Rénovation partielle des installations d’éclairage public

€397k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 31 October 2024 · ended around October 2025 · 12 months

Company selected

SAS BoironConstruction de réseaux électriques et de télécommunications · registered office Saint-Nabord (88200) · headcount 50 to 99 employees · SIREN 307350306

The competition

3 bids received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 8 by amount of the 51 contracts Vittel published for 2024. It belongs to the policy Town planning and housing.

Other contracts of SAS Boiron in Vittel

Rénovation partielle des installations d’éclairage public2024 · maximum over 5 months398€kRénovation et extension du réseau d’éclairage du parc thermal2022 · maximum over 7 months375€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : none