Public contracts of Voiron · 2019 · Construction and buildings

Réaménagement du 2e étage de la bourse du travail

€90k
maximum contract amount over 8 months — what was paid on it is not published
Signed on 23 December 2019 · ended around August 2020 · 8 months

Company selected

Far ElecTravaux d'installation électrique dans tous locaux · registered office Chabons (38690) · headcount 3 to 5 employees · SIREN 531092385

Number 9 by amount of the 43 contracts Voiron published for 2019.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.