Public contracts of Vourles · 2023 · Construction and buildings

Aménagement du parking paysager Rue Louis Vernay pour le compte de la commune de Vourles et de la CCVG

€188k
maximum contract amount over 2 months — what was paid on it is not published
Signed on 12 December 2023 · ended around February 2024 · 2 months

Company selected

Titulaire sans SIRET

The largest of the 4 contracts Vourles published for 2023. It belongs to the policy Streets and transport.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

The 2 lots : 135 €k · 53 €k

The filing gives no SIRET for the contractor: since we cannot check it is not a person, the name is not published.

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.